Site Formation and Infrastructure Works for the Development of ex­-Cha Kwo Ling Kaolin Mine Site (Phase 2)
Project Scope and Progress

  • Contract No. SD/2022/02
    Subject : Site Formation and Infrastructure Works for the Development of ex­-Cha Kwo Ling Kaolin Mine Site (Phase 2)
    Scope of Works :
    a)site clearance and formation, as well as construction of related retaining walls and slopes;
    b)construction of a carriageway with associated footpaths to connect Ko Ling Road and the development of ex-Cha Kwo Ling Kaolin Mine Site (Phase 2), and associated improvement works for nearby roads; and
    c)associated ancillary works including drainage works, sewerage works, waterworks and roadside greening works.
    Commencement Date : 31 July 2023
    Anticipated Completion Date : 2027
    Contract Sum : Around $680 million
    Consultant : AECOM Asia Co. Ltd.
    Contractor : Vibro Joint Venture (SD/2022/02)

Work Progress

2026/01

2025/12

2025/11

2025/10

2025/09

2025/08

2025/07

2025/06

2025/05

2025/04

2025/03

2025/02

2025/01

2024/12

2024/11

2024/10

2024/09

2024/08

2024/07

2024/06

2024/05

2024/04

2024/03

2024/02

2024/01

2023/12